Concrete Slab, Monolithic Footing & Rebar Calculator
Size ready-mix cubic yards (rounded to 1/4 yd), corner-deducted thickened-edge footings, 10-CY truck loads, 80-lb/60-lb bag counts, #4 rebar 20-ft sticks, 6-mil vapor barrier rolls, and #57 crushed stone tons with live plan and cross-section drawings.
Slab Geometry & Footing Specs
SHEET S-101Material Schedule Summary
AUTO-UPDATED- Main Slab Volume (4")
- 7.11 CY (192 cu ft)
- Monolithic Footing Extra
- +3.41 CY (92 cu ft)
- Net Concrete / Gross (+10%)
- 10.52 CY / 11.57 CY
- Ready-Mix Order (1/4 yd)
- 11.75 CY (2 trucks)
- #4 Rebar Grid + Perimeter (+10% lap)
- 1034 LF (52 x 20' sticks)
- 6-Mil Poly Vapor Barrier (20'x100')
- 1 roll (15% overlap)
- #57 Crushed Stone Base (4")
- 10.0 tons (7.11 CY)
- Control Joint Max Spacing
- <= 10'-0" OC (saw-cut)
Scaled Slab Plan & Monolithic Edge Section
MONOLITHIC EDGEIRC R506.1 & Sub-Base Field Notes
- 4" slab passes IRC R506.1 (3.5" min) for garages, ADUs, and patios. For 2-post automotive lifts or heavy shop machinery, increase to 5" or 6" with 4,000 PSI concrete.
- 4" compacted #57 crushed stone base meets IRC R506.2.2 (4" min) for sub-slab drainage and capillary break.
- Monolithic perimeter edge (12" wide x 16" total depth) includes 2 continuous #4 bars. Verify local frost-line depth (IRC R403.1.4.1) and maintain 3" minimum concrete cover to earth.
- Install 6-mil polyethylene vapor retarder (IRC R506.2.3) lapped 6" minimum at seams and taped. Saw-cut control joints every 10 ft OC (approx. 24x to 30x slab thickness) to limit shrinkage cracking.
Draft 2D/3D walls and layouts free with watermarked proof PNGs. Export clean
unwatermarked 2-sheet PDF from $9 one-time, or full 5-sheet vector
PDF + AutoCAD R12 .DXF + .CSV takeoff for $19.
Concrete Slab, Monolithic Footing & Rebar Takeoff Worksheet
- Slab Footprint: 24' x 24' (576 sq ft, 96 LF perimeter)
- Slab Thickness: 4" (7.11 CY) | IRC R506.1: PASS
- Monolithic Footing: 12" W x 12" below slab (16" total edge, 3.41 CY extra, corner-deducted)
- Ready-Mix Order: 11.75 CY (net 10.52 CY + 10% waste, rounded to 1/4 yd) | 2 x 10-CY trucks
- Bagged Concrete Alt: 521 x 80-lb bags or 695 x 60-lb bags
- #4 Rebar (18" OC Grid + 2 Perimeter Bars): 1034 LF (+10% lap) = 52 x 20-ft sticks
- Sub-Base & Vapor Barrier: 10 tons #57 stone (7.11 CY @ 4") | 1 x 20'x100' 6-mil poly roll
Preliminary space-planning & drafting worksheet. Verify all dimensions, structural spans, and local building codes on site with a licensed professional prior to construction.
US Residential Concrete Slab & Footing Reference Table
| Application | Typical Slab Thickness | Monolithic Edge | #4 Rebar Grid | Mix Strength & Base |
|---|---|---|---|---|
| 2-Car Detached Garage (24'x24') | 4" (IRC R506.1 min 3.5") | 12" W x 16" total depth | #4 @ 18" OC + 2 edge bars | 3,500 to 4,000 PSI over 4" #57 stone + 6-mil poly |
| Automotive Lift Shop (30'x40') | 6" heavy-duty slab | 16" W x 18" total depth | #4 @ 16" OC + 2 edge bars | 4,000 PSI min over 6" #57 stone (verify lift spec) |
| Barndominium / Shouse (40'x60') | 5" to 6" | 16" W x 17" to 18" depth | #4 @ 16" OC + 2 edge bars | 4,000 PSI over 6" #57 stone + 6-mil vapor barrier |
| Backyard ADU (28'x30') | 4" (insulated edge) | 12" W x frost depth | #4 @ 18" OC + 2 edge bars | 3,500 PSI + perimeter rigid foam per energy code |
| Back Patio / Walkway (16'x20') | 4" flat-edge slab | None (non-structural) | #4 @ 24" OC or fiber mesh | 4,000 PSI air-entrained (freeze-thaw) + 4" gravel |
Concrete Slab, Footing & Rebar FAQ
How do you calculate concrete cubic yards for a monolithic slab with thickened edges?
Compute the main slab volume (Length x Width x Slab Thickness in feet), then add the perimeter footing volume below the slab using the exact ring area (Outer Area minus Inner Area, which prevents double-counting the four corners) multiplied by the extra turndown depth. Divide total cubic feet by 27 to get net cubic yards, add 10% for waste and grade variance, and round up to the nearest 1/4 cubic yard for ready-mix delivery.
What slab thickness is required by IRC R506.1 for a residential garage, ADU, or shop?
IRC Section R506.1 specifies a minimum concrete floor slab thickness of 3.5 inches on ground, with 4 inches being standard for residential garages, ADUs, and patios. For detached workshops with 2-post automotive lifts, heavy machinery, or barndominium vehicle bays, 5 to 6 inches of 4,000 PSI concrete is commonly specified.
How much #4 rebar do I need for a 24x24 garage slab?
A 24 ft x 24 ft slab with #4 rebar at 18 inches on center requires 16 bars running each way (752 LF of grid) plus two continuous #4 perimeter footing bars (188 LF) if poured monolithically. Adding 10% for lap splices and corner hooks totals 1,034 linear feet, or 52 standard 20-foot sticks.
How many tons of #57 gravel do I need under a concrete slab?
IRC R506.2.2 requires at least a 4-inch base course of clean, well-draining crushed stone under interior slabs. Multiply slab square footage by gravel depth in feet, divide by 27 for cubic yards, and multiply by 1.4 tons per cubic yard for compacted #57 crushed stone.
When should I order ready-mix concrete trucks instead of 80-lb bags?
One cubic yard equals forty-five 80-lb bags or sixty 60-lb bags. Hand-mixing is practical only for small footings or pads under 1 to 1.5 cubic yards. Any full patio, garage, ADU, or barndominium slab over 2 cubic yards is faster, stronger, and more uniform when ordered from a ready-mix plant (standard US trucks hold up to 10 cubic yards).
Preliminary Space-Planning & Material Estimate: Preliminary space-planning and material estimate. Verify slab thickness, soil bearing, frost-depth footings, and reinforcement schedules with a licensed structural engineer and local building department.